Status of Project

Energy Audit of Campus
  • i.  Undertaken in June 2009.
  • ii. An entirely planned endeavor consisting of team visit to all Departments, Bhawans, Centers, etc.,
        interviewing of key personnel, use of power analyzer, lux meters, software, etc. for Data Collection, Data
        Analysis and Recommendations.
  • iii. Identification of areas of energy wastage and potential for energy savings.
  • iv. Recommendations were made to improve energy efficiency and Cost-Benefit analysis was done.

 Equipment  Number    Equipment  Number
 TUBELIGHT(CONVENTIONAL CHOKE)  13253    COMPUTER(CRT)  1263
 TUBELIGHT(ELECTRONIC CHOKE)  2821    COMPUTER(LCD)  1234
 CFL  5076    Printer  691
 LED FITTINGS  10    PROJECTOR_LCD  72
 M.H. DOWNLIGHTER  140    PROJECTOR_OHP  86
 INCANDESCENT LIGHTBULBS  725    SCANNER  106
 FAN (ELECTRONIC REGULATOR)  2949    SPEAKER SYSTEM  100
 FAN(RESISTANCE REGULATOR)  5740    REFRIGERATOR  95
 WALL FAN  216    WATER COOLER  214
 AC(SPLIT)  133    HEATER  35
 AC(WINDOW)  784    GEYSER  365
 ROOM COOLER  236    TELEVISION  15
 ROOM HEATER  210    COFFEE MACHINE  11
       WASHING MACHINE  09
  • * Key analysis included:
  • - Equipment, Application, Location wise analysis of campus.
  • - Separate analysis of Bhawans, Departments and Institute Central facilities.

Location wise Energy Consumption

Application wise Energy Consumption

  • * Key Recommendations included:
  • - Replacement of old appliances like monitors, lights, fan regulators, geysers, with energy efficient appliances.
  • - Use of motion sensors and master switches.
  • - Better practices for ACs.