Title |
2.2: Guidelines for Hydraulic design of SHP Projects |
|
Scope |
· Hydraulic Design of Head works including Intake - Gated Weirs - Trench Weirs - Bush & Boulder Weirs · Hydraulic Design of Trash racks · Hydraulic Design of - Headrace Channels - Headrace tunnels - Pipe conduits - Cross drainage works · Hydraulic design of bypass power channel including pilling works pertaining to development on existing canal falls · Hydraulic Design of Desilting Works - Vortex Tubes - Desilting tanks including flushing system · Hydraulic design of Forebay - Forebay - Spillway channel · Hydraulic Design of surge shaft · Hydraulic Design of penstock · Hydraulic Design of tailrace |
|
Status |
Draft issued on Feb 07, 2008 |
|
Committee |
1. Prof MK Mittal, Civil Engg. Department, IIT, Roorkee 2. Shri Pursothuman,AEE/Civil, Tamil Nadu Electricity Board,Chennai 3. Dr. B.N. Asthana, Former Chief Engineer, UP Irrigation, New Delhi 4. Mr Phil C Helwig, Consultant |
|
Remarks |
|